Estimating and Costing MCQ Questions & Answers

Estimating and Costing MCQ Questions & Answers

 

1. The rate of payment is made for 100 cu m (per % cu m) in case of

(A) Earth work in excavation
(B) Rock cutting
(C) Excavation in trenches for foundation
(D) All the above

Show Answer
(D) All the above

 

2. The rate of an item of work depends on

(A) Specifications of works
(B) Specifications of materials
(C) Proportion of mortar
(D) All the above

Show Answer
(D) All the above

 

3. The main factor to be considered while preparing a detailed estimate, is

(A) Quantity of the materials
(B) Availability of materials
(C) Transportation of materials
(D) All the above

Show Answer
(D) All the above

 

4. Pick up the correct statement from the following:

(A) The estimated value of the work excluding the amount for contingencies, work charged establishment, tool and plants, is called work value
(B) The actual expenditure involved to complete a work including incidental, establishment and travelling charges, is called actual cost
(C) The formal acceptance by the administrative department for incurring an expenditure on the work, is called administrative approval
(D) All the above

Show Answer
(D) All the above

 

5. Brick walls are measured in sq. m if the thickness of the wall is

(A) 10 cm
(B) 15 cm
(C) 20 cm
(D) None of these

Show Answer
(A) 10 cm

 

6. The plinth area of a building not includes

(A) Area of the walls at the floor level
(B) Internal shaft for sanitary installations up to 2 sq m. in area
(C) Lift and wall including landing
(D) Area of cantilevered porch

Show Answer
(D) Area of cantilevered porch

 

7. If the formation level of a highway has a uniform gradient for a particular length, and the ground is also having a longitudinal slope, the earthwork may be calculated by

(A) Mid-section formula
(B) Trapezoidal formula
(C) Prismoidal formula
(D) All the above

Show Answer
(D) All the above

 

8. While estimating a reinforced cement structure, the omitted cover of concrete is assumed

(A) At the end of reinforcing bar, not less than 25 mm or twice the diameter of the bar
(B) In thin slabs, 12 mm minimum or diameter of the bar whichever is more
(C) For reinforcing longitudinal bar in a beam 25 mm minimum or diameter of the largest bar which is more
(D) All the above

Show Answer
(D) All the above

 

9. A cement concrete road is 1000 m long, 8 m wide and 15 cm thick over the sub-base of 10 cm thick gravel. The box cutting in road crust is

(A) 500 m3
(B) 1000 m3
(C) 1500 m3
(D) 2000 m3

Show Answer
(C) 1500 m3

 

10. While estimating the qualities for the construction of a building, the correct metric unit is

(A) Metre for length
(B) Cubic metre for area
(C) Square metres for volume
(D) Litre for capacity

Show Answer
(D) Litre for capacity

Leave a Comment